Projects

Automated Fuel handling environments (AFHE) on DLA US Military fueling terminals on Okinawa

Project: Upgrade/Replace deteriorating motor operated valves, temperature probe, level gauge, high level switch conduits and wire infrastructure.

Prime contractor: KBR Inc. in support of DLA/Navy

Projects included trenching, concrete encasements, asphalt cutting and renewal, new UG & AG vinyl coated rigid metal conduits and fittings, pre-fab’d concrete handholes, MOV cutoff switches, new power wiring and new communications wiring from devices back to the Remote Interface Unit (RIU) and/or Power Junction boxes (PJB).

Click for larger image

Automated Vehicle Gates Kadena Airbase

Project: Upgrade flightline access control.

Prime contractor: Prometheus Security Group Global in support of 18th Security Forces

Projects (two complete) included installation of new gate posts, gate support hardware, motor operator, cantilevered vehicle slide gates, concrete pads, trenching, concrete encasements, asphalt cutting and renewal, UG & AG conduits for power and communications wiring from AVG to IDS panels & breaker panels, power and comm wiring and terminations, card readers and exit buttons.

Click for larger image

Generator replacement Kadena Airbase

Project: Replace non-procurable Cummings stand-by emergency generator

Prime contractor: Mediatti Broadband Communications Services (MBC)

Project included disconnecting old Cumming generator, removing fuels and oils, removing and re-locating old generator. Installation of new Cummings D6C 75kVa, fuels, fluids, cable re-terminations, load testing. This particular project will include quarterly and annual maintenance.

Click for larger image

Aerial Work

Replacing Aerial cable drops due to damage from typhoon.

  • Aerial Copper Construction
  • Replacing Aerial Supports
  • Terminating Cables on Poles and Houses
  • Testing Cables

Click for larger image

Security Camera Installation

Copper Cable Installation in Manhole System

  • Obtain confined space entry permits safety setup
  • Gas level checks
  • Manhole water pump
  • Rodding ducts
  • Installing pull rope
  • Pulling cable
`

Direct Burying Trunk Line in Family Housing

  • Removing and disposing excessive rocks and land
  • Trenching
  • Placing conduit with pull wire
  • Cable burial tape
  • Back filling and tamping
  • Obtaining proper clearances for trench work
  • Restoration of land to original condition

Cable Pulling

Fiber Pulling Fiber distribution at various locations

Soil Restoration

Land Reclamation

  • Removing old power lines
  • Removing old light
  • Removing old pole
  • Cutting and removing metal structures (with torch)
  • Restore land for future occupants

Consulting and Designing