Project: Upgrade/Replace deteriorating motor operated valves, temperature probe, level gauge, high level switch conduits and wire infrastructure.
Prime contractor: KBR Inc. in support of DLA/Navy
Projects included trenching, concrete encasements, asphalt cutting and renewal, new UG & AG vinyl coated rigid metal conduits and fittings, pre-fab’d concrete handholes, MOV cutoff switches, new power wiring and new communications wiring from devices back to the Remote Interface Unit (RIU) and/or Power Junction boxes (PJB).
Project: Upgrade flightline access control.
Prime contractor: Prometheus Security Group Global in support of 18th Security Forces
Projects (two complete) included installation of new gate posts, gate support hardware, motor operator, cantilevered vehicle slide gates, concrete pads, trenching, concrete encasements, asphalt cutting and renewal, UG & AG conduits for power and communications wiring from AVG to IDS panels & breaker panels, power and comm wiring and terminations, card readers and exit buttons.
Project: Replace non-procurable Cummings stand-by emergency generator
Prime contractor: Mediatti Broadband Communications Services (MBC)
Project included disconnecting old Cumming generator, removing fuels and oils, removing and re-locating old generator. Installation of new Cummings D6C 75kVa, fuels, fluids, cable re-terminations, load testing. This particular project will include quarterly and annual maintenance.
Replacing Aerial cable drops due to damage from typhoon.
Fiber Pulling Fiber distribution at various locations